Question 66
Which of the following data can be maintained in a standard network? Note: There are 3 correct Answers to this question.
Question 67
Where can you define a network as "header-account-assigned" or "activity-account-assigned"?
Question 68
Dates
You have a project with a network, material and milestone. You want to plan an activity to start two days after its predecessor. How can you do that?
Note : there are 2 correct answers for this question.
You have a project with a network, material and milestone. You want to plan an activity to start two days after its predecessor. How can you do that?
Note : there are 2 correct answers for this question.
Question 69
Where do you control whether a project stock is managed as valuated or non-valuated project stock?
Question 70
You want to make sure that certain tasks must start on a given date. Where can you maintain constraints for start dates?