Which of the following would MOST likely help provide benchmarking for a sustainable project?
Correct Answer: C
TheCMAA Standards of Practice (Chapter 8 - Sustainability and Environmental Stewardship) identifiesEnergy Staras one of the leading benchmarking systems for evaluating energy performance and sustainability in buildings. The SOP describes: "Benchmarking tools such as Energy Star and LEED provide measurable metrics for evaluating the energy efficiency and sustainability of a facility." TheEnergy Star program, administered by theU.S. Environmental Protection Agency, offers standardized methods to measure, track, and compare energy performance, making it the most directly relevant choice for sustainability benchmarking. References (CMAA Construction Manager Documents / Study Guide): CMAA Construction Management Standards of Practice, 2010 Edition, Chapter 8 - Sustainability and Environmental Stewardship, Section "Sustainability Metrics and Benchmarking Tools." CMAA CM Study Guide, Sustainability Domain, Objective 8.1: "Identify benchmarking tools for measuring sustainability performance."
Question 2
If it can be proven that there was discrimination based on gender during the hiring process, someone may lose their CCM credential due to a violation of the
Correct Answer: C
TheCCM Conditions, Conduct, and Disciplinary Policiesstate that any individual found to have breached the Conditions and Conduct agreement is subject to revocation of CCM status. The Conditions and Conduct agreement is essentially the Professional Code of Conduct (or Code of Professional Ethics) under which CCMs agree to operate. Discrimination, such as gender-based discrimination in hiring, is a violation of professional ethical standards and would be considered "unprofessional or unethical conduct" under the Code of Professional Conduct.
Question 3
The joint between a cast-in-place wall and a cast-in-place roof slab contains a waterstop for a sub-grade structure. While installing roof beams, the waterstop became dislodged from the already-placed wall. A non- conformance report was issued. The engineer of record's repair detail showed to cut and remove the dislodged waterstop sections. The authority/agency re-approved the detail as the waterstop is part of a secondary waterproofing system and the primary system was deemed sufficient. The contractor did not comply with the detail and placed the concrete roof slab over the dislodged material. In this scenario, which of the following options represents the BEST course of action?
Correct Answer: A
PerCMAA Standards of Practice (Chapter 5 - Quality Management and Chapter 6 - Contract Administration), when non-conforming work is discovered and the contractor fails to comply with approved corrective instructions, the appropriate procedure is for thecontractor to submit a proposed corrective action or repair detailfor review and approval by theengineer of recordand theowner. The SOP emphasizes: "The contractor is responsible for proposing a corrective action for nonconforming work. The CM shall ensure the proposal is reviewed and approved by the design professional and owner prior to implementation." Accepting the condition as-is (Option C) would be improper without formal approval, and unilateral removal or demolition (Options B or D) should only occur after the approved corrective process is completed. References (CMAA Construction Manager Documents / Study Guide): CMAA Construction Management Standards of Practice, 2010 Edition, Chapter 5 - Quality Management, Section "Nonconforming Work and Corrective Action." CMAA CM Study Guide, Quality Management Domain, Objective 5.4: "Coordinate the review and approval of corrective actions for nonconforming work."
Question 4
During the design phase, the CM should perform which of the following tasks?
Correct Answer: B
In theCMAA Project Managementchapter, during theDesign Phase, the CM's duties focus on evaluatingdesign progress, cost control, and schedule integration. The CMAA SOP specifies: "During the design phase, the Construction Manager should review design submissions for compliance with budget, schedule, and program requirements; participate in cost estimating and design coordination meetings; and support permitting and regulatory agency coordination." OptionBcorrectly reflects these core design-phase responsibilities: reviewing cost estimates, schematic design development, and attending scheduling or coordination conferences with agencies. The other options refer to administrative, construction-phase, or post-construction tasks, not design-phase CM functions. References: CMAA Construction Management Standards of Practice, 2010 Edition, Chapter 2 - Project Management, Section: "Design Phase Services," pp. 23-26. CMAA Study Guide, Project Management Domain, Objective 2.3.
Question 5
The CM is tasked with analyzing the schedule variance of a project on a regular basis. The contractor's recent payment application includes a dramatic increase in earned hours than what was budgeted for the project. This MOST likely indicates
Correct Answer: D
In earned value or earned hours analysis, "earned hours" represent how much work hasactuallybeen completed (in units of schedule effort) compared to what was budgeted over time. If a contractor claims a significantly higher number of earned hours than budget expected at that point, that discrepancy often indicatesthe contractor is catching up for prior slippageorback-loading progressand may be masking a delay. In other words, the project is likely behind schedule: the contractor is accelerating or shifting resources to show a jump in performance, sometimes to avoid triggering delay claims or escalating scrutiny. While CMAA's formal SOP does not provide a one-sentence treatment of this particular scenario, standard earned value (EV) and schedule variance (SV) theory (used in CMAA's time management domain) supports that an unexpected inflation in earned hours relative to budget can signal a retrospective correction for lagging progress, rather than true ahead-of-schedule condition.