Question 11
Program management includes the early participation of the program manager in developing and making which of the following types of decisions that become the basis of a capital improvement program?
Question 12
Which of the following contract types limits the potential incentive to increase profit through increasing contract costs?
Question 13
= P × [(C + T + Q) + 3]
P is Probability
C is Cost
T is Time
Q is Quality
This equation best describes a(n)
P is Probability
C is Cost
T is Time
Q is Quality
This equation best describes a(n)
Question 14
A construction manager is responsible for the bid review and evaluation of an $85 million high school project.
All bids must be submitted in person at the clients Purchasing Office by 1:00 PM EST and stamped by the CM's team. While preparing for the bid opening, the CM noticed that one of the contractor's bids was submitted a day earlier to a new clerk, but was date and time stamped after the bids were due. What should the CM do in this situation?
All bids must be submitted in person at the clients Purchasing Office by 1:00 PM EST and stamped by the CM's team. While preparing for the bid opening, the CM noticed that one of the contractor's bids was submitted a day earlier to a new clerk, but was date and time stamped after the bids were due. What should the CM do in this situation?
Question 15
Which of the following statements BEST describes the recommended approach CMs should take with respect to building information modeling (BIM)?