Question 26
You are setting your environment to use Resource Scheduling Optimization (RSO). You have enabled Optimize Schedule for all Bookable Resources.
You need to complete the remaining steps to prepare your work order data for optimization.
Which three actions should you perform, in sequence, to achieve the goal? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.

You need to complete the remaining steps to prepare your work order data for optimization.
Which three actions should you perform, in sequence, to achieve the goal? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.

Question 27
You are a Dynamics 365 for Field Service Dispatcher.
You need to use the schedule board to find resources for a work order. The work order can be completed by any resource who has the correct piece of equipment and who is available at 9:00 A.M during a selected week.
Which four steps must you take, in sequence, to successfully implement this capability within the schedule board? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.

You need to use the schedule board to find resources for a work order. The work order can be completed by any resource who has the correct piece of equipment and who is available at 9:00 A.M during a selected week.
Which four steps must you take, in sequence, to successfully implement this capability within the schedule board? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.

Question 28
You work for a recycling company that provides customers with large compactor units to collect their recyclable materials. The compactor units are comprised of two separate components: a container to collect the recyclable materials and a separate component that compacts the recyclable materials to make them easier to transport.
These containers are expensive, and the components tend to break down frequently, requiring ongoing maintenance and repairs.
You need to easily track the containers that your company has at each client location and maintain a service history for each of the sub-components.
These containers are expensive, and the components tend to break down frequently, requiring ongoing maintenance and repairs.
You need to easily track the containers that your company has at each client location and maintain a service history for each of the sub-components.
Question 29
You are Dynamics 365 for Field Service Administrator and work for a manufacturing company. The company provides customers with large power systems for sophisticated data centers. The power systems are serviced by a field engineering team.
The field engineering team documents work done on repairs and maintenance by completing Work Orders within Dynamics 365.
You need to easily schedule work orders for the field engineering team via the schedule and enable geocoding.
Which two steps must you take to schedule resources via the schedule board and enable geocoding? Each correct answer presents part of the solution.
The field engineering team documents work done on repairs and maintenance by completing Work Orders within Dynamics 365.
You need to easily schedule work orders for the field engineering team via the schedule and enable geocoding.
Which two steps must you take to schedule resources via the schedule board and enable geocoding? Each correct answer presents part of the solution.
Question 30
You are a Dynamics 365 for Field Service Administrator. You configure Route Scheduling Optimization (RSO) and publish the schedule.
One of your schedulers indicates two of their resources are not getting work orders assigned.
You need to determine Auto Geo Code Addresses to Yes in Field Servic rk orders through RSO.
Which three options should you choose? Each correct answer presents a complete solution.
One of your schedulers indicates two of their resources are not getting work orders assigned.
You need to determine Auto Geo Code Addresses to Yes in Field Servic rk orders through RSO.
Which three options should you choose? Each correct answer presents a complete solution.