Question 91

Your company is preparing to deploy the Dynamics Field Service with Mobile Application.
Your manager asks you to ensure that the Booking Statuses will match with the current business process the field technicians are following.
As the Field Service Administrator, you review the documentation and discover that the out-of-the-box BookingStatuses will meet your company's needs.
What is the order of the Booking Statuses for the five out-of-the box booking status fields? To answer, move the five out-of-the-box booking status fields to the answer area and arrange them in the correct order.

Question 92

You are a Dynamics 365 for Field Service Administrator.
You are setting up a new Incident Type. There are no service tasks or products created that are related to this incident.
Which seven actions should you perform in sequence to add these services? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
NOTE: More than one order of answer choices is correct. You will receive credit for any of the correct orders you select.

Question 93

You work for a digital billboard manufacturing company. When manufacturing is completed, the new digital billboards are shipped to a client site for installation. As the dispatcher for your company, you need to identify and schedule the different resources that are required to complete the installation of the digital billboard.
The installation of a billboard is a complicated process and requires a large team of resources all with different skills. These installations occur frequently, so you want to dispatch the resources for installations as efficiently as possible.
You need to configure multi-resource scheduling.
Which three steps should you perform, in sequence, to enable the multi-resource scheduling? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
Select and Place:

Question 94

You are implementing Microsoft Dynamics Field Service. You create a view of all scheduled work orders for a specific city on a specific day. You need to modify the view to show completed work.
Which field should you use to filter the view?