Question 91
You are the production scheduler at a manufacturing company. You schedule estimated production orders and ensure that capacity is used efficiently.
You have an order that must be scheduled at the resource group level and scheduled backward from the delivery date specified on the production order.
You need to schedule the order.
Which scheduling parameters should you use? To answer, select the appropriate option in the answer area.
NOTE: Each correct selection is worth one point.

You have an order that must be scheduled at the resource group level and scheduled backward from the delivery date specified on the production order.
You need to schedule the order.
Which scheduling parameters should you use? To answer, select the appropriate option in the answer area.
NOTE: Each correct selection is worth one point.

Question 92
A company produces pipe at certain fixed lengths.
The company must be able to schedule cutting machines. You set up the cutting machines as resources. All cutting resources can produce many of the products. There are some products that require cutting machines that can produce longer lengths of product. Only some of the machines can do this.
You need to configure the resources to account for these different products.
What should you do?
The company must be able to schedule cutting machines. You set up the cutting machines as resources. All cutting resources can produce many of the products. There are some products that require cutting machines that can produce longer lengths of product. Only some of the machines can do this.
You need to configure the resources to account for these different products.
What should you do?
Question 93
You need to configure costing for raw materials used to manufacture unscented cleaning solution.
Which form should you use?
Which form should you use?
Question 94
A company uses Lean manufacturing concepts to produce paper plates redesigned the layout of the warehouse and production floor.
The company's production flow activities no longer match the tasks of the workers Employees use paper and manual communication to complete the tasks.
You need to update the production flows to match their current processes by deactivating the obsolete production flows and creating new ones.
Which five actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.

The company's production flow activities no longer match the tasks of the workers Employees use paper and manual communication to complete the tasks.
You need to update the production flows to match their current processes by deactivating the obsolete production flows and creating new ones.
Which five actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.

Question 95
You are a production manager at a company which produces large batches of coffee and creamers.
After a quality inspection, batch 120008 of you cold brew coffee (item number CB-0001) was found to be too acidic and must be reworked.
You need to add 20 grams of sugar and stir the product for an additional 0.5 hours.
What three actions are required on the rework order? Each correct answer presents part of the solution.
NOTE: Each correct selection is worth one point.
After a quality inspection, batch 120008 of you cold brew coffee (item number CB-0001) was found to be too acidic and must be reworked.
You need to add 20 grams of sugar and stir the product for an additional 0.5 hours.
What three actions are required on the rework order? Each correct answer presents part of the solution.
NOTE: Each correct selection is worth one point.