Question 86
A manufacturer uses Dynamics 365 Supply Chain Management to create bicycle parts as a configure-to-order configuration. All bicycle parts are sourced from external sources and assembled in the manufacturing facility.
The manufacturer plans to expand its capabilities to create custom bicycles parts in an engineer-to-order model. All bicycle parts will be created in the manufacturing facility. The custom bicycle parts must be omitted from any master planning process.
You need to describe the concepts for the requirements.
Which concepts should you use? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.

The manufacturer plans to expand its capabilities to create custom bicycles parts in an engineer-to-order model. All bicycle parts will be created in the manufacturing facility. The custom bicycle parts must be omitted from any master planning process.
You need to describe the concepts for the requirements.
Which concepts should you use? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.

Question 87
A beverage company uses Dynamics 365 Supply Chain Management batch processing for production- You need to identify the ingredient type used in batch processing when the base attribute of a product is added to a formula line.
What is the ingredient type?
What is the ingredient type?
Question 88
You are a manufacturing consultant helping a client test out different bill of material (BOM) and route consumption options when starting production orders. Material and labor consumption are to be completed before Report as finish.
You are running a production order with BOM lines that have a Flushing principle set to Start. The Automatic Route Consumption Runtime has been set to Yes.
You have set up the default Start user options for all production orders as shown in the exhibit below.


You are running a production order with BOM lines that have a Flushing principle set to Start. The Automatic Route Consumption Runtime has been set to Yes.
You have set up the default Start user options for all production orders as shown in the exhibit below.


Question 89
A company implements Dynamics 365 Supply Cham Management.
You need to ensure that cost roll-ups and sales price calculations are configured for the scenario. Which options should you use? To answer select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.

You need to ensure that cost roll-ups and sales price calculations are configured for the scenario. Which options should you use? To answer select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.

Question 90
A company uses Dynamics 365 Supply Chain Management.
A piece of machinery that is critical to a production order breaks down during a production order.
The completed quantities of the production order must be shipped. The remaining quantity on the production order needs to be completed once the machinery is fixed. Negative inventory is not allowed for the items.
You need to resolve the production issue.
What should you do?
A piece of machinery that is critical to a production order breaks down during a production order.
The completed quantities of the production order must be shipped. The remaining quantity on the production order needs to be completed once the machinery is fixed. Negative inventory is not allowed for the items.
You need to resolve the production issue.
What should you do?