Question 106

An electronics manufacturing company is transitioning from infinite capacity planning to finite capacity planning to improve scheduling efficiency and manage resource constraints effectively.
The company observes that its manufacturing process typically requires a minimum lead time of five days.
The company requires finite capacity scheduling to create realistic production schedules that account for resource limitations over a defined minimum lead time of five days.
You need to implement finite capacity planning with a time fence that aligns with the five-day manufacturing lead time.
Solution: Disable finite capacity planning for all resources.
Does the solution meet the goal?
  • Question 107

    Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution. Determine whether the solution meets the stated goals. Some question sets might have more than one correct solution, while others might not have a correct solution.
    After you answer a question in this section, you will NOT be able to return to It. As a result, these questions will not appear in the review screen.
    A manufacturing company has a new speaker that is available with standard and premium carbon fiber options.
    For the premium option, speakers are made to order. Customers can choose from seven product attributes at different prices.
    You need to create and configure the product and pricing for the new speaker.
    Solution: Create a constraint-based product with configurations. Use a price model to calculate the different configurable option costs.
    Docs the solution meet the goal?
  • Question 108

    A manufacturer is implementing Dynamics 365 Supply Chain Management with warehouse management processes (WMS).
    Warehouse workers use hand-held devices to pick and stage batch-tracked products for production. The warehouse manager requires that products are removed from on-hand inventory and consumed when they are picked and staged for production.
    You need to remove the products from on-hand inventory.
    What should you configure?
  • Question 109

    A manufacturing company uses Dynamics 365 Supply Chain Management.
    The shop floor has multiple pieces of the same model of equipment. The equipment produces a finished good that requires special handling.
    The equipment has a visual guide available. The shop floor manager requires the following:
    * The most recent visual guide must be available for all pieces of the equipment at the same time.
    * The shop floor workers must have a visual guide available for handling of the finished good.
    You need to configure the visual guides to meet the shop floor requirements.
    What should you configure for each requirement? To answer, drag the appropriate features to the correct requirements. Each feature may be used once, more than once, or not at all. You may need to drag the split bar between panes or scroll to view content.
    NOTE: Each correct selection is worth one point.

    Question 110

    A pharmaceutical company is implementing Dynamics 365 Supply Chain Management.
    The formulas for medication include a single active ingredient. The active ingredient will be defined with a target level and specified deviation ranges from the target.
    You need to set up the active ingredient items.
    Which two actions must you perform? Each answer presents a partial solution.
    NOTE: Each correct selection is worth one point.