Question 41

After promoting their lift station design services to prospective clients, a new engineering Arm was hired by a local municipality to design and build a highly technical control system. ~me system required specialized electrical wiring and sot up, along with detailed programming.
The licensed professionals at the firm had newer dealt with such a complicated control system or set-up, but not wanting to lose their new client, proceeded with the design and set up without competent knowledge.
Delays on the project occurred due to the lack of satisfactory drawings and programming code. When the system was delivered and set up onsite. It failed to work properly despite various time-consuming adjustments. These delays led the firm to Dill the client for cost over-runs. In retrospect, what should the firm have done?
  • Question 42

    A licensed professional civil engineer is assigned by their employer to review and approve a building's structural design drawings. The design includes a vaulted component. Although the professional has not worked with vaulted designs in the past, they have recently completed an extensive "Cathedral and Vaulted Ceilings" engineering design course. The professional is confident in their knowledge and ability to competently review and assess this type of design.
    Is it appropriate for the professional to accept the current assignment?
  • Question 43

    A party bringing forward electronic documents as evidence in a court case needs to authenticate the electronic documents by
  • Question 44

    A licensed professional is asked by their employer to perform a professional task within their competency.
    The task is neither illegal nor in clear violation of their regulator's Code of Ethics; however, it does contravene the professional's personal moral code. The most appropriate action for the professional to take is to
  • Question 45

    The licensing process of most professional associations for engineers and geoscientists requires experience that meets various criteria. Which of the following examples wouldnotbe considered experience that satisfies the criteria "awareness of social implications of engineering" and "awareness of the societal implications of geoscience"?