Question 31
At XYZ Corp, multiple ClaimUnit sub case types are spun off from a parent Claim case. User retrieve ClaimUnit assignment using Get Next Work based on the average time to resolve each sub case type.
Assignments associated with sub case types that tale longer to resolve on average should be retrieve first. The average time to resolve sub case types will change over time. How do you design the solution to handle this requirement?
Assignments associated with sub case types that tale longer to resolve on average should be retrieve first. The average time to resolve sub case types will change over time. How do you design the solution to handle this requirement?
Question 32
XYZ Inc.'s COE wants case life cycle developers to use a field group named "Claim" regardless of the application being developed.
Select and move the three tasks that the COE performs for this requirement to the Task List column and place them in the correct order. (Choose Three)

Select and move the three tasks that the COE performs for this requirement to the Task List column and place them in the correct order. (Choose Three)

Question 33
A slow-running connector must run whenever the status of a case changes.
select the three steps to configure a solution that minimizes the delay experienced by the user
select the three steps to configure a solution that minimizes the delay experienced by the user
Question 34
You want to avoid creating unnecessary case-related properties and views. Which three actions do you take to accomplish this goal? (Choose Three)
Question 35
You are managing distributed, geographically dispersed, development teams A, B and C.
Team A is ready to merge changes into their development environment to make available changes to Team B's Team C's.
To ensure all development teams are working with the latest version of shared rule base, select and move all of the following tasks to the tasks List Order column and place them in the correct order.

Team A is ready to merge changes into their development environment to make available changes to Team B's Team C's.
To ensure all development teams are working with the latest version of shared rule base, select and move all of the following tasks to the tasks List Order column and place them in the correct order.