Question 181

Which of the following should be included in an effective SOW?
  • Question 182

    During the execution phase, the project manager discovered that the testing phase is dependent on completion of the vendor's tasks. The project team has just informed the project manager their activities are almost complete, and they would like permission to begin testing. The vendor is not scheduled to deliver the products for two months.
    Which of the following should have occurred to prevent this issue?
  • Question 183

    A project manager has been assigned a project with a budget of $50,000. Three change requests are submitted during execution that will increase the overall project cost to $60,000. Which of the following steps should the project manager perform NEXT?
  • Question 184

    Which of the following job roles is primarily tasked with communicating the project timeline changes?
  • Question 185

    Which of the following is the MOST likely target audience to be notified of the achievement of a key milestone in a project schedule?