Question 196
Which of the following are characteristics of a project? (Select TWO)
Question 197
A project manager has noticed poor attendance as status meetings.
Which of the following strategies should the project manager use to improve attendance? (Choose two.)
Which of the following strategies should the project manager use to improve attendance? (Choose two.)
Question 198
A project sponsor approved an undocumented change without following the formal change control process.
The resulting change caused an outage in a crucial accounting application. Which of the following change control processes would help mitigate the realization of this risk?
The resulting change caused an outage in a crucial accounting application. Which of the following change control processes would help mitigate the realization of this risk?
Question 199
A company purchased a parachute supplier and is now sending parachutes to the research and development department. Which of the following has occurred?
Question 200
In a project with a ВАС of $235,000, the CPI is 0.80, and the SPI is 1.20. Based on this information, which of the following can the key stakeholders determine about the project?