Question 21
There is a project in which the team can only meet once every three months. When the team does meet, no one can remember what was discussed and decided upon last time; thus, progress is being delayed. Which of the following project management tools would help?
Question 22
A team member learns that an assigned task is not due until the very end of the project.
Moreover, the team member is not aware of any predecessor tasks dependent on completing the assigned task. Which of the following does the project manager use to decide if the team member can start the task later or earlier?
Moreover, the team member is not aware of any predecessor tasks dependent on completing the assigned task. Which of the following does the project manager use to decide if the team member can start the task later or earlier?
Question 23
A project manager has taken over a project that is already in progress. The project manager notices the functional manager of one team is unaware of the current progress. Which of the following should the project manager do? (Choose two.)
Question 24
Gas prices were included in the cost baseline for a transportation and hauling project. Although the estimates used to create the baseline were based on historical data, which of the following should the project manager consider as a root cause for potential issues with cost overruns?
Question 25
A project manager is assigned to a project and has not had a handover meeting with the previous project manager. The new project manager is reviewing the percent of project completion, schedule progress, and budget constraints.
Which of the following documents should the project manager use to obtain this information?