Question 31
In which of the following organizational structures would a project manager have the MOST authority?
Question 32
Two team members completely disagree on how to complete a specific task. The project manager observes the conflict but takes no immediate action.
Which of the following techniques is the project manager using?
Which of the following techniques is the project manager using?
Question 33
A project has fallen behind schedule for no obvious reason, so the PM has gathered the team to brainstorm. Which of the following should the PM do NEXT?
Question 34
A senior developer abruptly resigned without notice. Because of the senior developer's expertise, the active task workload was substantial.
This would likely impact the project's: (Choose two.)
This would likely impact the project's: (Choose two.)
Question 35
An agreement document that is intended to prevent two or more organizations from sharing specific, confidential information with anyone but each other is called: