Question 146

A project manager is assigned to a project and has not had a handover meeting with the previous project manager. The new project manager is reviewing the percent of project completion, schedule progress, and budget constraints Which of the following documents should the project manager use to obtain this information?
  • Question 147

    There are four parallel paths on a network diagram. The summary duration of each path is below:
    A, C, G: 10 weeks
    A, B, F: 8 weeks
    D, E, H: 12 weeks
    D, B, F: 7 weeks
    Which of the following tasks are on the critical path?
  • Question 148

    A project's key stakeholders have requested significant changes that will affect the scope. To adjust the project scope, which of the following need to be changed? (Choose two.)
  • Question 149

    A key stakeholder asks the project manager for additional features. Which of the following documents should the project manager refer to before responding to this request?
  • Question 150

    Which of the following describes a burn rate?