Question 186
A part that is needed to complete Task 3 has been backordered and will arrive three days later than scheduled. Task 3 must be complete for Task 4 to start. There is one day of float for the two tasks.
Which of the following represents the number of days the project schedule will be delayed?
Which of the following represents the number of days the project schedule will be delayed?
Question 187
A project coordinator notices there is a scheduling conflict with the weekly team meeting. The project coordinator submits a request to hold the meeting at a different time will not negatively impact the scheduling.
Which of the following resources has the authority to authorize this change?
Which of the following resources has the authority to authorize this change?
Question 188
A project manager is managing a project with a hard deadline in two weeks. At the current rate of progress, the project will not finish on time Which of the following techniques is
MOST likely to be used to complete the project on time?
MOST likely to be used to complete the project on time?
Question 189
Ann, a customer, approaches the project manager of a portable computing device implementation project with a request to have a tablet instead of a laptop.
Which of the following steps should the project manager take NEXT?
Which of the following steps should the project manager take NEXT?
Question 190
A project manager is justifying a required change with the associated impact on the project.
Which of the following is the NEXT step?
Which of the following is the NEXT step?