Question 206

A stakeholder is unaware of a project's status.
Which of the following documents should the project manager consult to ensure all stakeholders are notified of project changes? (Choose two.)
  • Question 207

    A project is running behind schedule. To meet the delivery timelines, the project manager decides to give part of the work to another organization for quicker delivery and to allow the project team to focus on the remaining tasks. This is an example of:
  • Question 208

    Which of the following risk strategies prevents a risk from impacting a project?
  • Question 209

    A project manager received a change request, immediately documented the required changes, and evaluated the impact of and justification for the changes.
    Which of the following should the project manager do NEXT?
  • Question 210

    A project team is comprised of a mix of in-house and virtual team members.
    When a complex announcement needs to go out to the entire project team, which of the following is the MOST effective way to communicate it?