Question 226

A project requires daily status updates.
Which of the following is the MOST effective method for providing these updates?
  • Question 227

    Which of the following project management tools provides an authoritative source of the project performance guidelines?
  • Question 228

    There are four parallel paths on a network diagram. The summary duration of each path is below:
    A, C, G: 10 weeks
    A, B, F: 8 weeks
    D, E, H: 12 weeks
    D, B, F: 7 weeks
    Which of the following tasks are on the critical path?
  • Question 229

    The following tasks are required to complete an IT project that is behind schedule:

    Which of the following is the critical path?
  • Question 230

    A project team has completed a major deliverable earlier than planned and wants to deliver it for testing. The team lead sends an email providing notice of task completion to the project manager.
    Which of the following describes how the project manager can increase the likelihood that the deliverable moves to testing?