Question 51
During the execution phase of a project, a project task has run longer than anticipated.

Which of the following is the new critical path of the project if Task 2 requires an additional two days to complete?

Which of the following is the new critical path of the project if Task 2 requires an additional two days to complete?
Question 52
A project manager is sending regular status reports; however, many team members seem to be unaware of the overall project status. Which of the following should the project manager do NEXT?
Question 53
During a project assessment, a project manager determines the initial project cost estimates were incorrect, and there is not enough budget left, including reserves, to complete the project.
Which of the following actions should the project manager take?
Which of the following actions should the project manager take?
Question 54
A company hires an outside vendor to provide 24/7 support.
Which of the following documents would determine the contractual obligations?
Which of the following documents would determine the contractual obligations?
Question 55
A project manager is assigned to a project and has not had a handover meeting with the previous project manager. The new project manager is reviewing the percent of project completion, schedule progress, and budget constraints.
Which of the following documents should the project manager use to obtain this information?
Which of the following documents should the project manager use to obtain this information?