Question 26

When a buyer requests a potential seller to provide details related to a product, service, or seller capability, which of the following documents would be used?
  • Question 27

    A company has hired a new project manager. The PMO has briefed the new project manager on the following expected responsibilities for projects:
    * Coordinate project schedule
    * Manage to the triple constraint
    * Provide performance feedback to team members' managers
    Which of the following types of organizational structures did the new project manager MOST likely join?
  • Question 28

    During a meeting, the project manager abruptly interrupts the discussion of two team members who have not reached an agreement on a particular requirement and continues with the meeting.
    Which of the following conflict resolutions is the project manager performing?
  • Question 29

    A project team member highlights to the project manager that expensive licensing for critical software in use across the project may exp.re before the completion of the project.
    Which of the following would the project manager MOST likely do?
  • Question 30

    A project manager is informed that a team member would like to enhance the code with an additional function. Which of the following should the project manager do NEXT?