Question 86
A sponsor requests that the project team shorten the completion of a project by two months to give the sales team more leverage in renegotiating the contract with the client. The budgeted time is 500 hours, and the projected earned value is $30,000.

Which of the following represents the cost variance for both project completions?

Which of the following represents the cost variance for both project completions?
Question 87
The project manager has noticed a vendor is not performing in accordance with the SLA.
Which of the following items should the project manager use to highlight the vendor's areas of poor performance?
Which of the following items should the project manager use to highlight the vendor's areas of poor performance?
Question 88
An employee is assigned to a project and is developing a project charter. Which of the following are some of the constraints the employee would typically face at this stage of the project?
Question 89
During an ad-hoc meeting, the PM notifies the sponsor that while the project is on schedule, material costs have increased and the project is over budget. To save the project, the PM request a material contract with a less expensive vendor. The sponsor approves the change, and project comes in within target tolerances. The company, however, receives numerous stakeholder complaints.
Which of the following is the MOST likely cause of these complaints?
Which of the following is the MOST likely cause of these complaints?
Question 90
An organization has multiple projects that are taking place simultaneously.
Which of the following should be tasked with ensuring resources are appropriately allocated to projects?
Which of the following should be tasked with ensuring resources are appropriately allocated to projects?