Question 116
A project has come to a close, and the project manager is evaluating each team member. After completing the evaluations, the results are emailed to the supervisor and used for yearly evaluations. Which of the following organizational types is being described?
Question 117
A new high-priority project is assigned to the project manager with a fully formed budget, deadline, and scope. The project manager is creating the project schedule.

Which of the following calculations accurately shows the critical path?

Which of the following calculations accurately shows the critical path?
Question 118
A change must be made to a project to comply with municipal code. The project manager updates the relevant shared project documents. The key stakeholders subsequently update the documents with new information. When the project deliverables are reinspected, they fail the inspection. Which of the following is the MOST likely reason for the failed inspection?
Question 119
Which of the following events would MOST likely trigger communications to the largest audience for a given organization?
Question 120
Which of the following roles has approval authority for project funding?