Question 136

Which of the following describes how a project is related to a program?
  • Question 137

    A WBS is being developed for a project.
    Which of the following would be BEST suited to contribute cost and time estimates for the project activities?
  • Question 138

    A project manager must create documentation before the project kickoff meeting. Which of the following documents will identify the project, introduce the project manager, and establish authority in the project?
  • Question 139

    The project manager for a multinational project is evaluating the option of scheduling face quick responses to issues. Which of the following strategies is being applied?
  • Question 140

    Which of the following documents is a snapshot in time of a project during the execution phase?