Question 86

The final project report should contain which of the following?
  • Question 87

    An authorized change to a construction project was implemented. During the modification, the team identified a defect in which the change caused the building power output to be outside the KPPs.
    Which of the following actions should the project manager take?
  • Question 88

    A project team learns that potential remodeling on the production floor might occur during the execution phase of their project. The project team starts debating the different options available to keep delivering without adjusting the schedule. Which of the following risk activities is being performed?
  • Question 89

    Two team members are arguing over two different approaches to complete a task. The project manager listens to both sides, determines neither approach will work, and directs the team members to use a third option.
    This type of conflict resolution is known as:
  • Question 90

    On an OBS chart, there is a dashed line between some team members and the project manager, and there is a solid line connecting other members to the project manager. Additionally, some employees at a lower level on the chart have no connection to the project manager.
    Which of the following does this signify?