Question 96

Which of the following organizational changes is MOST likely used to transfer staff resources from one city to another to support team activities?
  • Question 97

    A sensitive project requires activities to occur with very specific, to-the-minute timing. Which of the following would BEST ensure on-time delivery?
  • Question 98

    A project is coming to the end of a phase. The PMO requires that the quality team review the work and budget before moving on to the next phase of the project. The project manager must schedule the review of the phase and have the stakeholders present.
    This review is referred to as:
  • Question 99

    A project manager is assigned to a project that was previously managed by a peer project manager. The project manager identifies several modifications that were deployed prior to CCB approval. Which of the following change control processes is being mismanaged?
  • Question 100

    A project team has completed a major deliverable earlier than planned and wants to deliver it for testing. The team lead sends an email providing notice of task completion to the project manager.
    Which of the following describes how the project manager can increase the likelihood that the deliverable moves to testing?