Question 126
An organization recently restructured. Leaders feel they are not in a position to sign off on a required change, which is delaying a project.
Which of the following is the obstacle?
Which of the following is the obstacle?
Question 127
A project manager is working on a project, which needs to be delivered within six months. The project sponsor has made it known that the six months is non-negotiable and additional funding can be provided, if required.
The project is in the fifth month, and testing is ongoing. The project team has identified a major defect that will take up to one month to rectify.
Which of the following is the BEST action for the project manager to take to ensure the project finishes as planned?
The project is in the fifth month, and testing is ongoing. The project team has identified a major defect that will take up to one month to rectify.
Which of the following is the BEST action for the project manager to take to ensure the project finishes as planned?
Question 128
A project manager at a projectized organization is finishing the objective goals for the appraisal process. Performance goals have been identified for colocated individuals working on the team. Which of the following is the appropriate communication method for relaying the goals to the team members?
Question 129
At a weekly project team meeting, it is apparent the project is over budget. The project manager needs to determine the reason for this issue. Which of the following documents should MOST likely be analyzed to obtain the answer?
Question 130
Which of the following tools would a project manager use to determine the root cause of an issue?