Question 131

At a project kickoff meeting, several team members acted unprofessionally. The project manager would like to set expectations for team interaction. Which of the following would BEST accomplish this?
  • Question 132

    Using Scrum, which of the following are discussed in a daily standup meeting?
  • Question 133

    A new project manager would benefit from additional assistance with documenting project activities.
    Which of the following job positions should the project manager request be added to the team?
  • Question 134

    The design activity of a project has the following cost attributes:
    PV = 100,000
    EV = 20,000
    AC = 90,000
    Based on this scenario, calculate the schedule variance.
  • Question 135

    A senior developer abruptly resigned without notice. Because of the senior developer's expertise, the active task workload was substantial.
    This would likely impact the project's: (Select two.)