Question 131
At a project kickoff meeting, several team members acted unprofessionally. The project manager would like to set expectations for team interaction. Which of the following would BEST accomplish this?
Question 132
Using Scrum, which of the following are discussed in a daily standup meeting?
Question 133
A new project manager would benefit from additional assistance with documenting project activities.
Which of the following job positions should the project manager request be added to the team?
Which of the following job positions should the project manager request be added to the team?
Question 134
The design activity of a project has the following cost attributes:
PV = 100,000
EV = 20,000
AC = 90,000
Based on this scenario, calculate the schedule variance.
PV = 100,000
EV = 20,000
AC = 90,000
Based on this scenario, calculate the schedule variance.
Question 135
A senior developer abruptly resigned without notice. Because of the senior developer's expertise, the active task workload was substantial.
This would likely impact the project's: (Select two.)
This would likely impact the project's: (Select two.)