Question 156

A project manager realizes there is a significant risk event. Which of the following is the FIRST step the project manager should perform?
  • Question 157

    A fire alarm goes off in the building where the project team works. Employees are instructed to leave the premises immediately using the stairs; they are not to use elevators, and they must gather in one place outside the building for further instructions. This is known as a:
  • Question 158

    The PMO has asked the PM to provide a status report indicating the number of events and activities required to complete a project. Which of the following charts should the PM include in the status report?
  • Question 159

    The PM is preparing for the planning phase kickoff meeting. It is imperative for the team to focus during the meeting on the expected outcomes.
    Which of the following best describes what the PM should work on FIRST?
  • Question 160

    A procurement project manager presents the project status at a steering committee review. One of the defined risks is becoming an issue. The steering committee provides feedback and agrees on a mitigation plan. After reviewing the meeting minutes and project documents, a new risk is created. Which of the following needs to occur FIRST?