Question 1
A project manager has been informed that the delivery of required IT equipment will be delayed. Which of the following is the FIRST step the project manager should take?
Question 2
After a release, the project sponsor received an escalation from an executive about the extension of the
downtime after the scheduled window. Which of the following should be added to the issue log?
downtime after the scheduled window. Which of the following should be added to the issue log?
Question 3
A third party needs to perform a short-term task for which the duration cannot be accurately estimated and the
cost cannot be calculated in advance. Which of the following should the project manager put in place before
work begins?
cost cannot be calculated in advance. Which of the following should the project manager put in place before
work begins?
Question 4

Given the following network diagram:
Which of the following is the critical path?
Question 5
A customer requests some changes to a product, and those changes are approved by the CCB. Which of the following should be changed first?