A team member identifies a critical issue in production. Which of the following should the project manager apply?
Correct Answer: C
A rollback plan, also known as a backout plan, is a strategy designed to reverse changes made during a project in case of failure or undesired results1. A rollback plan is a form of risk response that allows the project to restore the previous state and minimize the impact of the issue. A rollback plan is usually created during the planning phase and implemented during the execution or closing phase of the project. The other options are not correct because: A compliance check is a process that ensures that the project meets the relevant standards, regulations, and requirements. A compliance check is not a risk response, but rather a quality control or assurance activity. A release plan is a document that outlines the scope, schedule, and resources for delivering a product or service to the customer. A release plan is not a risk response, but rather a communication or scope management tool. A validation check is a process that verifies that the project deliverables meet the customer's needs and expectations. A validation check is not a risk response, but rather a quality control or assurance activity. References = CompTIA Project+ Study Guide: Exam PK0-005, 3rd Edition, Chapter 10: Executing and Closing Projects, page 314; CompTIA Project+ Certification Exam Objectives, Domain 3: Project Execution, Objective 3.2: Given a scenario, execute and monitor project tasks using traditional methodologies; Backout Plan - DevX
Question 252
As part of the planning phase, a PM has defined tasks, durations, resources, and costs. Which of the following is the NEXT step in the process?
Correct Answer: C
The next step in the process after defining tasks, durations, resources, and costs is to seek baseline approval. A baseline is an approved version of a project plan that serves as a reference point for measuring progress and performance throughout the project lifecycle. A baseline typically includes scope, schedule, cost, quality, and risk parameters. Seeking baseline approval involves presenting the project plan to key stakeholders and obtaining their formal agreement on the project objectives and deliverables. Baseline approval can help to establish clear expectations, avoid scope creep, and facilitate change control during project execution. The NEXT step after defining tasks, durations, resources, and costs during the planning phase is to seek baseline approval. Baseline approval involves finalizing the project plan and gaining approval from stakeholders, establishing the plan as the baseline for the project's performance. References: CompTIA Project+ Study Guide Section 3.4.1
Question 253
Which of the following describes three-tier architecture?
Correct Answer: B
Presentation, application, and data processing. Presentation, application, and data processing are the three logical and physical computing tiers that make up a three-tier architecture. A three-tier architecture is a type of software architecture that separates an application into three layers or tiers that run on different servers or machines. Each tier performs a specific function or role and communicates with other tiers through well-defined interfaces. The presentation tier is the user interface and communication layer of the application, where the end user interacts with the application. The application tier is the logic or middle tier of the application, where data is processed using business rules. The data processing tier is the data or back-end tier of the application, where data is stored and managed12
Question 254
Which of the following BEST identifies the intent and purpose of a project closeout report?
Correct Answer: C
Explanation To validate that a project has been successfully completed. The intent and purpose of a project closeout report is to validate that a project has been successfully completed and to summarize the goals, objectives, and outcomes of the project, as well as the lessons learned and the feedback from stakeholders. A project closeout report is a document that is submitted at the end of a project to officially conclude it and release the resources and contracts involved. It is useful for evaluating the project's success and improving the performance of future projects12
Question 255
A sponsor is working on a document that states the objectives and success criteria of the project, as well as the person to be appointed as project manager Which of the following should the newly appointed project manager do next?