Question 36

A project's first iteration contains item A, and its second iteration contains item B.
The first iteration is behind schedule, which will impact the second iteration. Since items A and B are similar, a team member suggests beginning the design of item B.
What should the agile practitioner do?
  • Question 37

    The Project Leader's primary responsibilities are to "move boulders and carry water". What is this an example of?
  • Question 38

    The product owner should spend at least 3 hours per day with the development team?
  • Question 39

    What can an agile team use to prioritize stories?
  • Question 40

    A product owner feels that the last sprint failed to sufficiently deliver what was valuable to their organization's overall project goals.
    What should the scrum master mention at the next retrospective?