Question 126

During iteration planning, the team is discussing the design for a user story. A team member states that a design document should be started since the system is complex in nature. Another team member responds that in Agile there is no documentation. How should the ScrumMaster respond?
  • Question 127

    Who is responsible for determining the business value of each feature?
  • Question 128

    More details for a story are required before the upcoming sprint planning meeting. What should the scrum master do?
  • Question 129

    Which of the following is an example of an information radiator?
  • Question 130

    The Product Owner and Scrum Master are never part of the Development Team.