Question 186
A large project team of 20 people from different functional areas has just been formed and the project starts next week. The team will be working on a regulated and strictly controlled pharmaceutical product but does not have subject matter expertise. Which two actions should the scrum master take as priorities? (Choose two.)
Question 187
An organization is using a predictive approach to managing projects. The executives like to see more deliverables in a short time and require that the milestones be achieved on time.
What value can the organization gain by moving to an iterative approach?
What value can the organization gain by moving to an iterative approach?
Question 188
An organization is undergoing an agile transformation to improve its market position. Management wants minimal overhead in connection with the agile initiative and wants the agile teams to control the work in process (WIP) and ensure that iterations do not result in waste.
Which approach should be used in this scenario?
Which approach should be used in this scenario?
Question 189
A backlog for a project has been prioritized and a sprint has begun. A security issue has been revealed that needs to be addressed or large security vulnerabilities will be exposed.
How should the project manager proceed?
How should the project manager proceed?
Question 190
A project has several features that will deliver immediate customer value. The product owner needs to determine which features to include in the upcoming iteration.
What should the product owner have the customer review and approve?
What should the product owner have the customer review and approve?