Question 41

Which document best provides the boundaries for product development?
  • Question 42

    Once the requirements are compared to internal and external quality standards, what should the business analyst do next?
  • Question 43

    A new business analyst has taken over on a project that is in the development phase. The project manager is looking for an update on requirements status.
    What should the business analyst use to help communicate the status?
  • Question 44

    Which of the following tools will help facilitate the decision-making process when stakeholders do not agree on the value of an initiative?
  • Question 45

    Company A is working on implementing a new platform with multiple stakeholders. The business analyst has gathered the requirements and established a baseline. However, scope creep is a persistent problem.
    What could the business analyst have established to help manage this situation?