Question 71

The project manager is beginning to prepare for a test readiness review with the customer. The project manager knows that the customer will want a summary of requirements that have been rejected or deferred.
The project manager has requested that the business analyst provide a list of rejected and deferred requirements.
What should the business analyst have done to complete this request?
  • Question 72

    Midway through Ihe requirements gathering phase, a stakeholder informs the business analyst that a requested requirement does not address the solution. The stakeholder wants to know who made the request. The business analyst spends hours searching emails to identity the requestor.
    What should the business analyst have documented?
  • Question 73

    A business analyst is working on a project to implement a new call management system for a help desk.
    They expected the average time interval to answer a call to decrease over time, but the interval has increased instead.
    Which technique should the business analyst use to investigate the problem?
  • Question 74

    A company is developing a new risk management system. The company expects the system to evolve in the near future due to changing government regulations.
    Which approach will better cope with the requirements' volatility?
  • Question 75

    Which of the following actions will contribute most to the success of the initial stage of the project?