Question 66

You are the project manager of the NHQ project for your company. Management has told you that you must implement an agreed upon contingency response if the Cost Performance Index in your project is less than
0.90. Consider that your project has a budget at completion of $250,000 and is 60 percent complete. You are scheduled to be however, 75 percent complete, and you have spent $165,000 to date. What is the Cost Performance Index for this project to determine if the contingency response should happen?
  • Question 67

    You are the project manager of the NHK Project. Management wants to know how often your risk identification process will occur during the project. Considering that your project is scheduled to last one year and involvs five distinct phases, how often should risk identification take place?
  • Question 68

    Donna is the project manager of the QSD Project and she believes Risk Event D in the following figure is likely to happen.

    If this event does happen, how much will Donna have left in the risk contingency reserve if none of the other risk events have happened?
  • Question 69

    The risk manager is about to go on medical leave, but before departing, conducts a risk response planning review meeting with stakeholders. A new risk manager is assigned to the project, and during the first status meeting an issue is identified.
    What is the appropriate course of action in this case?
  • Question 70

    Donna is the project manager of the QSD Project and she believes Risk Event D in the following figure is likely to happen.

    If this event does happen, how much will Donna have left in the risk contingency reserve if none of the other risk events have happened?