Question 46
When monitoring the execution quality of risk-related plans and processes, which of the following would be a useful metric to track and record?
Question 47
You are the project manager of the BJA Project for your company. Management is worried about one of the identified risks in your project. The risk event has a probability of 90 percent and a cost impact of $85,000.
Management and you discuss possible solutions to address the risk. You share with them that for $75,000 you can reduce the probability of the risk event to 15 percent and the impact to $25,000. This solution will add three weeks to the project schedule. Management thinks this is a good idea and they would like you to add the time and cost additions to your project plan. What type of risk response is used?
Management and you discuss possible solutions to address the risk. You share with them that for $75,000 you can reduce the probability of the risk event to 15 percent and the impact to $25,000. This solution will add three weeks to the project schedule. Management thinks this is a good idea and they would like you to add the time and cost additions to your project plan. What type of risk response is used?
Question 48
A cost analyst team member asks the project manager for the latest risk data for inclusion with the cost estimates for the project. Which tool should the cost analyst team member use to identify the probability of achieving specific cost targets?
Question 49
You work as a project manager for BlueWell Inc. You are preparing for the risk identification process. You will need to involve several of the project's key stakeholders to help you identify and communicate the identified risk events. You will also need several documents to help you and the stakeholders identify the risk events.
Which one of the following is NOT a document that will help you identify and communicate risks within the project?
Which one of the following is NOT a document that will help you identify and communicate risks within the project?
Question 50
Consider a project with a budget at completion of $1,345,000 and it is supposed to be completed by today, but it is only 80 percent complete. This project has spent $1,250,000 to reach this point of completion. What is the schedule variance for this project?