Question 66

During project execution, the project team realizes that the power outlet for imported equipment is not compatible with the current customers electrical infrastructure. This event was not originally identified as a risk.
To maintain the project schedule, the project manager decides to purchase a new power adapter.
What type of response best describes this course of action?
  • Question 67

    How can the project manager rank competing stakeholder priorities for all the identified risks?
  • Question 68

    Eric is the project manager of the MTC project for his company. In this project a vendor has offered Eric a sizeable discount on all hardware if his order total for the project is more than $125,000. Right now, Eric is likely to spend $118,000 with vendor. If Eric spends $7,000 his cost savings for the project will be $12,500, but he cannot purchase hardware if he cannot implement the hardware immediately due to organizational policies. Eric consults with Amy and Allen, other project managers in the organization, and asks if she needs any hardware for their projects. Both Amy and Allen need hardware and they agree to purchase the hardware through Eric's relationship with the vendor. What positive risk response has happened in this instance?
  • Question 69

    You work as a project manager for BlueWell Inc. You are working with your team members on the risk responses in the project. Which risk response will likely cause a project to use the procurement processes?
  • Question 70

    Kelly is the project manager of the BHH project for her organization. She is completing the risk identification process for this portion of her project. Which one of the following is the only thing that the risk identification process will create for Kelly?