Question 86
A risk manager is managing risks in a project. During the initial stages of project execution, a new risk is identified. There is a very small chance that this risk will occur and even if it occurs, the impact would be low.
What should the risk manager do with this risk?
What should the risk manager do with this risk?
Question 87
David is the project manager of the NKL Project for his organization. He has been asked to create a proposal for a construction project for a client. David realizes that there are several requirements within the SOW and RFP provided by the client that would eliminate his company from bidding on the construction project. David proposed to management that his organization create a partnership with a competitor so that together they could bid on the construction project and qualify for the customer's requirements. What risk response is David proposing to management?
Question 88
Adrian is a project manager for a new project using a technology that has recently been released and there's relatively little information about the technology. Initial testing of the technology makes the use of it look promising, but there's still uncertainty as to the longevity and reliability of the technology. Adrian wants to consider the technology factors a risk for her project. Where should she document the risks associated with this technology so she can track the risk status and responses?
Question 89
For the last several months, a project manager for a global technology program is focused on improving the project outsourcing process and analyzing the vendor supply chain as key pieces of the cost containment strategy. Early in the project, these two areas were identified as key risks to the final delivery of the project.
Since that initial risk identification, the risk manager works to identify additional risks, as well as analyze the potential impact to the project cost baseline. After performing a cost-risk sensitivity analysis, the risk manager produces this chart.

Based on this analysis, which two risk areas should the project manager focus on to control project cost?
Since that initial risk identification, the risk manager works to identify additional risks, as well as analyze the potential impact to the project cost baseline. After performing a cost-risk sensitivity analysis, the risk manager produces this chart.

Based on this analysis, which two risk areas should the project manager focus on to control project cost?
Question 90
What would be the next step after determining the agreed-upon risk response for a specific risk?
Premium Bundle
Newest PMI-RMP Exam PDF Dumps shared by BraindumpsPass.com for Helping Passing PMI-RMP Exam! BraindumpsPass.com now offer the updated PMI-RMP exam dumps, the BraindumpsPass.com PMI-RMP exam questions have been updated and answers have been corrected get the latest BraindumpsPass.com PMI-RMP pdf dumps with Exam Engine here: