Question 876

In WBS diagramming, the work package is:
  • Question 877

    You are using three point estimating technique to estimate the duration of a schedule activity.
    Which of the following statements are true given the following data:
    Pessimistic: 100 days Optimistic: 40 days Most likely: 65 days Average: 68.33 days Variance: 151.38
  • Question 878

    The project planning is progressing. The team has involved the accounting department to set up a system of codes that the accounting department will use to track work on the project. This is known as what?
  • Question 879

    You are in the process of developing an approximation of the costs of resources needed to complete each schedule activity. Which of the following is the LEAST helpful input?
  • Question 880

    You are in the process of controlling changes to the project cost baseline. Which of the following is the LEAST helpful tool / technique?