Question 106

You are the Project Manager on a merger and acquisition project. Activity A (3 days) and activity B (4 days) can start immediately. Activity C (2 days) can start after A and B are complete. Activity D (5 days) can begin after activity B is complete. Activity E (6 days) can begin after activity B is complete. Activity F (4 days) can begin after activities C and D are complete. Activity G (5 days) can begin after activities D and E are complete.
Activity H (4 days) can begin after activities F and G are complete. If Activity D increases from five to eight days, what is the critical path, and what is the length?
  • Question 107

    Which of the following are NOT considered formal types of project ending?
  • Question 108

    Standard deviation of project completion is _____ .
  • Question 109

    In the below path convergence example, if the odds of completing activities 1, 2, and 3 on time are 50 percent, 50 percent, and 50 percent, what are the chances of starting activity 4 on day 6?
  • Question 110

    A project needs preventative actions to meet security requirements and to avoid corrective actions if audited.
    One of the stakeholders does not agree with the success criteria.
    How should the project manager capture the performance in the closure report?