Question 906

Approved change requests, approved corrective actions, and updates to organizational process assets are all outputs of which project management process?
  • Question 907

    Deflection involves the transfer of risk by:
  • Question 908

    A primary function of a project management office is to support project managers in a variety of ways, including which of the following?
  • Question 909

    You are using the three-point estimating technique to estimate the duration of a schedule activity. You are given the following data: Pessimistic=200days Optimistic=100days Most likely=120 days Average= 130 days Variance= 277.7 Which of the following statements are true?
  • Question 910

    The estimate costs process uses all the following tools and techniques EXCEPT______________