Question 921

The best approach to resolve the settlement of all outstanding contract changes, claims, and disputes is using______________
  • Question 922

    The change control board (CCB) has just approved a change that will cause some rework, and the project team is not in total agreement with the change. What should the project manager do?
  • Question 923

    During a project meeting, the project manager asks risk owners to present issues that may affect the backlog.
    During their presentation, the project manager realizes that some risk owners did not implement the already agreed-upon risk responses.
    What should the project manager do to reduce exposure?
  • Question 924

    During each phase, what should a project manager do to avoid the reoccurrence of a consistent issue?
  • Question 925

    Which can be used to determine whether a process is stable or has predictable performance?