Question 106

Activities on the critical path have which type of float?
  • Question 107

    A key project stakeholder requests that the project management plan ensures that actions are taken to prevent defects. What should the project manager use to document how the project will demonstrate compliance with this requirement?
  • Question 108

    A few months into a project, several schedule issues have emerged Drag the schedule problems on the left to the specific tools on the right that if implemented during schedule development could have prevented the issues.

    Question 109

    The Project Manager and team are planning a banking software project. They are discussing what could go differently than planned on the project. They are also trying to identify warning signs that would show that these events could be on the verge of occurring. What are these warning signs called?
  • Question 110

    The team has implemented a risk response plan when a vendor was unable to fulfill a contract commitment. The response was to choose another vendor. Because of the short notice, the other vendor cannot fulfill the need of the team. Which best describes what happened with the different vendor?