Question 116
Qualitative risk analysis requires accurate data as its input. Risk Data Quality Assessment is a technique to evaluate the degree to which the data regarding risks would be useful. What is the best course of action if the Risk Data Quality Assessment for most of the identified risks are low?
Question 117
The project manager of a technical team receives a complaint from sensor team members. They state that while the majority of the team is committed, some of the junior members arrive late, spend excessive time on the Internet, and have high absenteeism and low productivity. This causes more work for the members who now threaten to leave the project if the situation does not improve.
Which the following should the project manager do to address this situation?
Which the following should the project manager do to address this situation?
Question 118
The PV is $1000, EV is $2000, and AC is $1500. What is CPI?
Question 119
Which of the following is a statistical concept that calculates the average outcome when the future includes scenarios that may or may not happen?
Question 120
A large matrix organization is adopting a new communications approach. This is necessary because their projects often require the resourcing of expert knowledge in the form of specialists from various departments and divisions.
What should the project manager do to set up effective communications?
What should the project manager do to set up effective communications?