Question 141
A project manager notices that work started by the project team is misaligned with an industry regulation. The project manager recalls that this topic was previously discussed during a stakeholder a stakeholder meeting.
What should the project manager review?
What should the project manager review?
Question 142
A project sponsor informs the project manager that the equipment delivered as part of the project failed to meet the customer's performance expectations. What should the project manager do first?
Question 143
A project manager has just been assigned to a team that is developing a new design product. The work breakdown structure (VW/BS) has been created and the activities have been assigned to the team members.
The project manager finds that there are activities that could be completed sooner by other team members. If the current assignments are left as is, the project could be delayed 2 weeks.
What should the project manager do in this situation?
The project manager finds that there are activities that could be completed sooner by other team members. If the current assignments are left as is, the project could be delayed 2 weeks.
What should the project manager do in this situation?
Question 144
A project is staffed with people from different countries, and several issues arise due to diverse approaches toward everyday activities. What should the project manager do to improve team performance?
Question 145
The sponsor is worried about the seller deriving extra profit on the cost plus fixed fee (CPFF) contract. Each month the sponsor requires the project manager to submit CPI calculations and an analysis of the cost to complete. The project manager explains to the sponsor that extra profits should NOT be a worry on this project because: