Question 11
The software development company has recently been awarded a large contract to create a new animation software program. This will require the company to move into a new office complete with production facilities twice their current size. The schedule is tight for this new project. The new facility is behind schedule with the cubicles and network wiring on pace to finish three weeks late. If this can't be done on time and will slip three weeks, the company has decided there is nothing it can do, and it will simply deal with the consequences. This is an example of what type of risk response?
Question 12
Project alternatives are examined during the _____ phase of the project
Question 13
A hospital is running a project for one of their internal critical systems to manage billing patient data and record management along with consultation reports and input from physicians The project manager now needs to categorize the identified risks Drag each risk type on the left to its correct example on the right


Question 14
Which is another term for top down estimating.
Question 15
Contract negotiations are NOT required when______________

