Question 31

You have been assigned to a project that will allow job seekers to fill out applications and submit them via the company website. You report to the VP of human resources. You are also responsible for screening applications for the information technology division and setting up interviews. The project coordinator has asked for the latest version of your changes to the online application page for his review. Which organizational structure do you work in?
  • Question 32

    The members of your project team have been assigned to your project with general availability levels of 50%.
    Yesterday, they reported to you that significant variances occurred during project execution. You observed that the team members are spending less than 50% of their time working for your project. Your project schedule is on the way to become heavily delayed and deadlines are in jeopardy. What should you do?
  • Question 33

    An advertiser who uses a movie or sports star to endorse a product is trying to use power.
  • Question 34

    A project manager realizes that the team members are new to the hybrid approach and do not value standup meetings. Team members often arrive late. Digress into solutioning. or skip the meetings altogether.
    How should the project manager improve this situation with the project team?
  • Question 35

    The stakeholder register should not be prepared only one time, but it should be updated regularly especially if______________