Which stakeholder communicates with higher levels of management to gather organizational support and promote project benefits?
Correct Answer: B
Question 777
Drag the characteristics of the stage on the left to the correct Tuckman Ladder stage on the right
Correct Answer:
Question 778
A risk was identified at the beginning of a project, and a response plan was established. Unforeseen consequences resulted in a higher level of risk. The project manager has an idea that could address the new risk in an efficient way, but the response is different from the original risk mitigation plan. What should the project manager do?
Correct Answer: B
When a project encounters a risk that was not fully anticipated, and the project manager has developed a new response that deviates from the original plan, it is essential to obtain management approval before proceeding. This ensures that the new approach is aligned with the project's objectives and that management is aware of the changes being made to the risk response plan. The PMBOK Guide highlights the importance of involving project stakeholders, particularly management, when significant changes are proposed1. This is also supported by best practices in business analysis, which advocate for stakeholder engagement and approval in the decision-making process to address risks effectively2. References: * PMBOK Guide, 6th Edition, Project Management Institute. * Professional in Business Analysis (PMI-PBA) resources, Project Management Institute.
Question 779
All the following are tools and techniques for performance reporting EXCEPT
Correct Answer: A
Question 780
A new project needs to be submitted for urgent funding approval. The project, which will use a new technology, is vital to the organization. The entire Scrum team has worked together for over 3 years on multiple projects and delivered the previous project under the approved budget. Which estimation technique should the project manager implement in this context?
Correct Answer: C
In the context of a project that involves new technology and an experienced Scrum team, the most suitable estimation technique is using story points. This method allows the team to leverage their collective experience and familiarity with each other's work to estimate the effort required for tasks relative to each other. Story points reflect the complexity, effort, and uncertainty of the task, making them ideal for projects where the technology is new and exact estimates are challenging to produce. Since the team has a history of successful collaboration, their established velocity can help predict how quickly they can work through the backlog. References: The use of story points is supported by Agile methodologies and is a common practice in Scrum teams for estimating work effort. This approach is detailed in the Agile Practice Guide, which is a complementary document to the PMBOKGuide, provided by PMI for understanding Agile practices in project management. The choice of story points over other estimation techniques is also consistent with the principles outlined in the PMI's Professional in Business Analysis (PBA) Reference Materials, which emphasize the importance of leveraging team expertise and past performance to inform project estimates.