Question 951

The following is a network diagram for a project.

The free float for Activity E is how many days?
  • Question 952

    A project manager receives information in preparation for reporting the project's monthly performance to the project steering committee.
    + Actual progress = 2 units
    + Planned progress = 3 units
    + Actual cost (AC) = 2 units
    + Budgeted cost = 3 units
    What statement should the project manager make to the project steering committee?
  • Question 953

    What name(s) is (are) associated with the Plan-Do-Check-Act cycle?
  • Question 954

    An established project team with a good track record has been working on a project for one year The project manager trusts the team and the work they produce. Which term describes the project manager's management approach?
  • Question 955

    A large global organization developed a new medical implant that requires compliance with local government regulations. The approval process for one country is lengthy and will impact the intended launch date.
    What should the project manager do?